AutoTrak® System with
CoPilot™ Module Saves $12.5 Million, Exposes 26,000 Ft of Reservoir
in Norwegian Tri-Lateral Well Location: Troll Field, Norway
Customer: HYDRO
Challenges:
- Drill complex tri-lateral reservoir sections
- Optimally position well bore within tight tolerances
- Minimize high local doglegs caused by calcite
- Complete well with screens in each lateral
|
|
Contact Information |
|
 |
|
|
Solution:
-
INTEQ’s Advanced AutoTrak integrated BHA with
LWD
-
Included the CoPilot™ drilling dynamics system
positioned close to the bit
-
Hughes Christensen bit program
-
EXCLUDER2000™ screen from Baker Oil Tools with
Inflow Control Devices
Results:
-
Drilled a total of 7950m (26,000 ft) of
reservoir
-
Three horizontal sections optimally positioned
-
Used only three AutoTrak® RCLS tool strings
-
Effectively used CoPilot system to avoid high
local doglegs
-
Four Genesis™ HCR607 bits averaged 1968m/bit on
lateral sections
-
Finished 35.5 days ahead of time curve
-
Installed 9100 m of screen and gas lift system
without problems
-
Total well cost savings: $12.5 million
Baker Hughes helped HYDRO drill this complex
tri-lateral well 35.5 days ahead of schedule, then helped complete
all three legs with horizontal sand control technology. A close
cooperation with Smedvig and other service providers greatly
contributed to this success.
 |
|
|
 |
|