Image
Image
refineries_and_petrochemical_plants_istock-943356040_8.jpg
Eyebrow
Orbit Article

Reliability improvement for reciprocating compressor in CCR reformer process

Sang
Sang Joo Lee
Rotating Machinery Engineering Team Leader


SK Energy: Founded as the first oil company in South Korea in 1962, SK energy has been producing various petroleum products at the Ulsan Complex, which has a refining capacity of 840,000 barrels of crude oil per day, selling them in both domestic and overseas markets.

In response to the demand for increased production, the three reciprocating booster gas compressors in the Continuous Catalyst Regeneration (CCR) reformer process had been operating unspared, without backup, since a revamping project in 2009. Subsequently, the number of unplanned downtime incidents and related costs began to increase due to the number of unexpected failures and ensuing maintenance actions. In fact, the three CCR compressors consumed up to 90% of the maintenance costs out of 100 reciprocating compressors in the plant.

This article describes how SK Energy overcame the challenges in process control, mechanical design, and condition monitoring for the reciprocating compressors to improve the reliability of those assets and reduce the maintenance cost.

Machine Description

The three reciprocating compressors in the CCR reformer process were installed in 2005. The booster compressors in CCR reformer process transfers rich hydrogen(H2) gas from reactor to H2 plant.

compressor-specification.png
Figure 1. CCR reformer process diagram

 

Problem Statement

Since the machines were revamped in 2009 to increase the production capability, these three compressors have been operated unspared. However, the number of machine problems increased drastically. Most problems were identified as damaged valves and cracked pistons.

Following the revamping project, the pressure ratios did not change significantly, but, discharge temperatures were all observed to have increased slightly higher than the original levels. After the revamping project, the discharge temperature setpoint was set at 145 °C.

table-2.png
Table 2. Machine revamp 2009

 

figure-2_0.png
Figure 2. Maintenance events on the booster compressor 2009-2016

 

figure-3_1.png
Figure 3. Failure modes distribution 2009-2016

 

figure-4.png
Figure 4. Damaged parts on 3 booter gas compressor

 

Cause and effect Analysis

SK Energy carried out a cause-and-effect analysis to identify the root cause of the recuring valve and cracked piston rod problems, covering every aspect of the process and the mechanical design & integrity of the compressor.

Process

Through the process review, it was found that an increase in Iron(III), oxide(Fe2O3) and Chloride(Cl2) dust contributed to polymerization of a green oil residue, due to changed process conditions. Also found that the Hydrogen/Hydro Carbon(H2/HC) ratio is one factor which could increase light olefins, another factor in formation of green oil. 

figure-5.png
Figure 5. H2/HC ratio in process gas composition

Fe2O3 was generated in the pipe by exposure to the atmosphere during turnaround, and the Cl2 dust was created during initial period of start-up, and by using new catalyst type. The Fe2O3 and Cl2 dust are catalysts which lead to formation of viscous green oil which collects as condensate in the compressor cylinder.

Machine Design & integrity

Before the revamping project, a concentric ring type discharge valve was used, however the valve was found to be not strong enough to endure foreign substances.

  • Sticking occurs due to foreign substance between valve sheet (seat) and ring.
  • Late opening and differential pressure increase between A and B area (refer Figure 7).
  • Increase impact and tumbling between the ring and guard. (Because outer ring's stiffness is lowest, outer ring breaks easily.)
figure-6.png
Figure 6. Valve failure on discharge valve

One of the unique features of these compressors' design is the use of a Free-Floating Piston (FFP). Because of the unique operation, the piston is made of lightweight material. It was determined that the material strength was not enough to withstand the large stress exerted by the green oil. 

figure-7.png
Figure 7. Piston failure due to green oil

 

Improvement

Based on what was found during the investigation phase, the following actions were taken for both the process side and mechanical integrity side. In addition to these, the Condition Monitoring system was upgraded to precisely monitor the condition of the machines.

Process

To avoid further generation of green oil, catalysts like Fe2O3 and Cl2 were completely purged from the piping system and the knockout drum to the discharge line during turnaround maintenance.  

image-8.png
Figure 8. Water washing and purging on the pipe

 

figure-9.png
Figure 9. Improve pipe line cleaning

 

To minimize the formation of green oil, the reformer process reduced the amount of light olefin and adjusted the operating conditions at startup to reduce chloride (Cl).

Machine Design & integrity

Replaced the original concentric ring valves with a poppet type valves which have high reliability under liquid carry-over and sticking scenarios.  

figure-10.png
Figure 10. Improve valve type

 

Improved the geometry of the piston to increase its mechanical strength. As the material and method of production changed, the strength increased ~48% above original and without weight change.

figure-11.png
Figure 11. Improve the geometry

 

In addition, to further improve the strength, the piston manufacturing process was changed to a drop forging method, resulting in a 26% strength improvement over the original cast design.

table-3.png
Table 3. Improve the material of piston

 

Condition monitoring system for reciprocating compressor

The original condition monitoring system could monitor only frame & crosshead vibration and simple process conditions (Suction & differential pressure, discharge temperature). Root-cause diagnosis could not be done due to the limited system.

table-4.png
Table 4. Instrumentation List for improvement

 

figure-12.png
Figure 12. Machine Diagram in Bently Nevada System 1

 

A permanent reciprocating compressor monitoring and diagnosis system was recommended. It included measuring and logic for installed cylinder pressure indicators, dual plane rod position and multi-event-wheel (MEW) key phasor. The corresponding diagnostic software, Bently Nevada System 1, allows precision diagnosis to be performed through P-V diagram analysis, and monitoring compressor events and vibration per each degree of crank angle.

Below are the advanced diagnostic variables enabled in System 1 software on a fully instrumented reciprocating compressor with cylinder pressure transducers and MEW Keyphasor:

  • Discharge Volumetric Efficiency
  • Suction Volumetric Efficiency
  • Indicated Horsepower
  • Adiabatic Discharge Temperature
  • Discharge Capacity
  • Suction Capacity
  • Median Capacity
  • Adiabatic Median Capacity
  • Flow Balance
  • Adiabatic Flow Balance
  • Power to Median Capacity
  • Indicated Clearance Volume
  • Discharge Power Loss
  • Suction Power Loss

Based on the review, it was determined that the maximum pressure inside the chamber tended to increase over normal values whenever a foreign substance entered the chamber, and subsequently deposited or built up around the discharge valve, preventing the valve from operating properly. Therefore, it was postulated the effective compression ratio was higher than typical ratio of discharge pressure to suction pressure due to the stiction effect (sticky valves), which in turn resulted in more heat of compression until the sticking discharge valves opened.  

figure-13.png
Figure 13. Determine valve maintenance timing

 

Based on Bently Nevada's recommendations and its technical review, rod position proximity probe transducer pairs and a cylinder pressure transducer at each chamber were newly installed to verify piston rod behavior and valve condition. Before this improvement, the available quantitative data was not enough to make an accurate assessment. With the enhancement to online condition monitoring parameters, it was demonstrated that chamber pressure measurements could give rich information in terms of compression performance as well as valve condition.

 

Outcome
figure-14.png
Figure 14. Outcome of the improvement

Soon after unit revamping in 2009, maintenance costs on these three compressors increased over 30 times due to the abovementioned process and mechanical problems. Through the condition monitoring improvement in 2016, the unit saw a reduction to just four maintenance incidents per year and zero cracked pistons. Those are the lowest numbers for the last 10 years, an outstanding outcome which can be attributed to the successful and collaborative cross-discipline efforts.

For this reciprocating compressor in CCR reformer process, the following considerations were key to the successful reliability improvement outcome:

Process
  • Optimize operating condition to minimized liquid carry-over
  • Purge the piping system to reduce catalyst of green oil after turn-around
Mechanical design
  • Based on the improvement, a piston with higher strength of material was needed in case foreign substance come in.
  • The ring-type valve was not strong enough when external foreign substances came in.
Condition monitoring
  • Ability increased to discuss with quantitative data which came from System 1 and process data. The calculated variables due to the pressure measurement give plenty of information for each throw on the machine which was able to determine a corrective action to take.
  • Also, pressure monitoring in System 1 gave an exact timing to do maintenance for the valves using the P-V diagram.

 

figure-15.png
Figure 15. Outcome of valve replacement

 



Our Experts


Image
sangjoo_lee.jpg

Sang Joo Lee

Rotating Machinery Engineering Team Leader

BIO

Rotating machinery engineering team leader for SK Energy Ulsan complex, Korea, since 2007. In charge of machine troubleshooting, reliability improvement, vibration analysis and technical consultant across SK sites.



Image
sangwook_lee.jpg

Sang Uk Lee

Rotating Machinery Engineering Team

BIO

Rotating machinery engineering team for SK Energy Ulsan complex, Korea, since 2012. Experience includes troubleshooting for a variety type of machines with vibration diagnosis in refinery and petrochemical plants.




Copyright 2022 Baker Hughes Company. All rights reserved. Baker Hughes provides this information on an “as is” basis for general information purposes. Baker Hughes does not make any representation as to the accuracy or completeness of the information and makes no warranties of any kind, specific, implied or oral, to the fullest extent permissible by law, including those of merchantability and fitness for a particular purpose or use. Baker Hughes hereby disclaims any and all liability for any direct, indirect, consequential or special damages, claims for lost profits, or third party claims arising from the use of the information, whether a claim is asserted in contract, tort, or otherwise. Baker Hughes reserves the right to make changes in specifications and features shown herein, or discontinue the product described at any time without notice or obligation. Contact your Baker Hughes representative for the most current information. The Baker Hughes logo, the Bently Nevada logo, and System 1 are trademarks of Baker Hughes Company.