Overview


Challenges
  • Mechanical seal leakage during flushing
  • Multiple failures
Results
  • Changes were made to the shaft material, heating coil system, and mechanical seal allowance, as well as modulation of the fresh feed input temperature
  • No more failures were experienced, and there was minimal impact on plant layout or costs




Case study details

A refinery in Italy had been using our 6x15 10-stage DDHF charge pump to process a combined feed at approximately 350°C. This kind of process pump must be warmed up by the hot-oil coil system and warming connections before starting and kept warm when in standby mode (approximately 60°C lower than the operating temperature).

During flushing, the pump had experienced mechanical seal leakage at the drive-end side, and wear patterns were observed on backstop.

We conducted a combined transient thermal and structural simulation analysis to distinguish the criticalities during warm-up procedures.

 